As presented as the April 21, 1998, public
working session of the Emergency Transitional Education Board of TrusteesCapital Work
Scheduled for Summer 98
|
| Repairs of Eastern SHS Windows | Start: May 98 | Completion: June 98 |
| Modular Chillers (2 - Summer Schools) | Start: June 98 | Completion: June 98 |
| 25 Roof Replacements | Start: June 98 | Completion: October 98 |
| 3 Window Replacements | Start: June 98 | Completion: September 98 |
| 2 Asbestos Abatement | Start: July 98 | Completion: October 98 |
| 2 ADA Compliance | Start: July 98 | Completion: October 98 |
| 2 Structural Repairs | Start: June 98 | Completion: September 98 |
| 3 Interior Finishes | Start: July 98 | Completion: October 98 |
| Key Activities | Time Lines | Executive Summary |
15 Boiler Projects in 19 Schools
|
June Start March 99 Completion | As need Temporary heat will be provided by contractor(s) |
| 6 Emergency Generators | July Start October Completion | Emergency Generators will not hinder School Operations. These new generators will serve as back up power to meet Fire Code Requirements |
3 Chillers
|
July Start January 99 Completion | These chillers are not essential for this Summer Operations and school activities |
11 Window Projects
|
July Start January 99 Completion |
![]()